The East Side Water Treatment project required the construction of a 650,000 gallon potable water treatment plant and a 530,000 gallon storage tank. The goal of the project was to increase water treatment capacity for the Village of Wonder Lake.
Project Location
Wonder Lake, IL
Project Scope
The scope included the construction of a 3,500 sq. ft. water treatment building and installation components including pumps, piping, HVAC, electrical, and controls equipment. Exterior site work included underground water distribution piping, applicable valve vaults, sanitary piping, electrical service ducts, site grading, asphalt parking lot, security fencing and landscaping.
Stats
- Project Type: Water & Wastewater Treatment
- Location: Wonder Lake, IL
- Project Value: $4.8M
- Duration: 11 months